ATLDOT Boone Blvd Resurfacing / Restriping Project
- HHHNA VP
- 4 hours ago
- 1 min read
The City of Atlanta Department of Transportation (ATLDOT) will resurface Joseph E. Boone Boulevard NW from Hamilton E. Holmes Drive NW to Northside Drive NW. The resurfacing project provides ATLDOT with the opportunity to restripe the street and to install safety improvements to make the street safer for all users. This project will be delivered in multiple
phases:
• Phase 1: Resurface and restripe from Northside to Joseph E. Lowery (Anticipated Fall 2025)
• Phase 2: Reconstruct roadway from Joseph E. Lowery to Mayson Turner (Anticipated End of 2025/Early 2026)
• Phase 3: Resurface and restripe from Joseph E. Lowery to Hamilton E. Holmes (Anticipated Before Summer 2026)
The third and final community engagement will held [in-person only] at Rambo Recreation Center in Dixie Hills on Monday, November 10.
See below for more info:




Next are maps of Segment 4, between Chappell Road to Mayson Turner Road, to provide context on how construction will impact our community.